A Project team has completed the project network diagram; what is the next thing to do?

[A] O Determine critical path
[B] O Develop budget
[C] Estimate time and c0st
[D] O Develop schedule

Choice C is the correct answer.

Project network diagram defines activity sequencing only. Critical path can be determined only after activity duration estimating is completed. Schedule and budgets are developed after completing risk management planning.

Hence choice C is correct while choices A, B, and D are incorrect.